Action Date | Action Description |
---|---|
Jul 18, 2012 | Maintenance Certification Request |
Jul 19, 2012 | Administrative Review for Completeness |
Jul 19, 2012 | Team Review for Completeness |
Jul 19, 2012 | Team Review for Completeness |
Jul 23, 2012 | Deficient Application - Owner Notification Sent |
Feb 26, 2013 | Deficiency Response Received |
Mar 06, 2013 | Team Review for Completeness |
Mar 06, 2013 | Application Accepted |
Mar 15, 2013 | 30 day Public Notice Issued |
Mar 21, 2013 | HPHC Historical Preservation No Effect |
Apr 08, 2013 | Public Notice End Date Extension Granted |
Apr 15, 2013 | Public Notice End Date |
Jun 04, 2013 | Additional Information Received |
Jun 07, 2013 | Biologist Report |
Jun 07, 2013 | Engineering Report |
Jun 10, 2013 | Typist for Processing |
Jun 10, 2013 | Permit Approved |
Jun 11, 2013 | Executive Sign Off |
Jun 11, 2013 | Sent to Photo Copy |