Action Date | Action Description |
---|---|
Administrative Review for Completeness | |
Oct 04, 2012 | Assent Application Received |
Oct 09, 2012 | Application Accepted |
Oct 09, 2012 | Category B assigned |
Oct 09, 2012 | Team Review for Completeness |
Oct 19, 2012 | HPHC Historical Preservation No Effect |
Jun 07, 2013 | Plans Received |
Jul 01, 2013 | Engineering Report |
Jul 01, 2013 | Executive Signoff of Staff Reports |
Jul 30, 2013 | Ready to Schedule Semi-Monthly Meeting |
Aug 07, 2013 | 30 day Public Notice Issued |
Aug 21, 2013 | Mail Agenda Notice |
Sep 07, 2013 | Public Notice End Date |
Sep 10, 2013 | Council Approval Granted |
Sep 10, 2013 | Semi-Monthly Meeting Held |
Sep 10, 2013 | Semi-Monthly Meeting Date Scheduled |
Sep 26, 2013 | 30 Day Appeal Notification to Owner |
Sep 26, 2013 | Legal Response/Decision |
Oct 08, 2013 | Stipulation Package by Engineer |
Oct 16, 2013 | Typist for Processing |
Oct 16, 2013 | Permit Approved |
Oct 22, 2013 | Executive Sign Off |
Oct 22, 2013 | Sent to Photo Copy |
Dec 16, 2013 | Land Evidence Date |
Feb 25, 2014 | Modification Request |
Feb 27, 2014 | Team Review for Completeness |
Feb 27, 2014 | Administrative Review for Completeness |
Mar 04, 2014 | Assent Correction Mailed |
Mar 06, 2014 | Land Evidence Date |
Jan 21, 2016 | US Army Corps of Engineers Approval Received |