Action Date | Action Description |
---|---|
Jan 18, 2013 | Assent Application Received |
Jan 22, 2013 | Administrative Review for Completeness |
Jan 23, 2013 | Team Review for Completeness |
Jan 23, 2013 | Team Review for Completeness |
Jan 23, 2013 | Deficient Application - Owner Notification Sent |
Feb 01, 2013 | Deficient Application Picked Up |
Aug 27, 2013 | Deficiency Response Received |
Sep 05, 2013 | Team Review for Completeness |
Sep 05, 2013 | Application Accepted |
Oct 08, 2013 | Additional Information Received |
Oct 23, 2013 | Biologist Report |
Oct 24, 2013 | Typist for Processing |
Oct 24, 2013 | Permit Approved |
Oct 25, 2013 | Executive Sign Off |
Oct 25, 2013 | Sent to Photo Copy |
Oct 30, 2013 | Land Evidence Date |
Oct 30, 2013 | HPHC Historical Preservation No Effect |