Action Date | Action Description |
---|---|
Feb 05, 2013 | Freshwater Wetland - Preliminary Determination |
Feb 06, 2013 | Administrative Review for Completeness |
Mar 08, 2013 | Plans Received |
May 06, 2013 | Additional Information Received |
May 08, 2013 | Objections/Comments Received |
May 08, 2013 | Application Accepted |
May 08, 2013 | Team Review for Completeness |
May 08, 2013 | Team Review for Completeness |
May 09, 2013 | Additional Information Received |
Jun 10, 2013 | HPHC Historical Preservation No Effect |
Jul 03, 2013 | Objections/Comments Received |
Aug 06, 2013 | Additional Information Received |
Dec 10, 2013 | 30-Day Notification of Cancellation letter |
Dec 23, 2013 | Certified Receipt Received |
Jan 13, 2014 | Additional Information Received |
Mar 13, 2014 | Additional Information Received |
Mar 28, 2014 | Biologist Report |
Mar 28, 2014 | Engineering Report |
Apr 02, 2014 | Supervisor Engineer SignOff |
Apr 02, 2014 | Supervisor Biologist SignOff |
Apr 03, 2014 | Executive Signoff of Staff Reports |
Jul 28, 2014 | Ready to Schedule Semi-Monthly Meeting |
Aug 12, 2014 | Mail Agenda Notice |
Aug 26, 2014 | Council Approval Granted |
Aug 26, 2014 | Semi-Monthly Meeting Held |
Aug 26, 2014 | Semi-Monthly Meeting Date Scheduled |
Sep 30, 2014 | Stipulation Package by Engineer |
Oct 14, 2014 | Legal Response/Decision |
Oct 20, 2014 | Stipulation Package from Biologist |
Oct 21, 2014 | 30 Day Appeal Notification to Owner |
Oct 21, 2014 | Legal Response/Decision |
Oct 23, 2014 | Typist for Processing |
Oct 23, 2014 | Executive Sign Off |
Oct 23, 2014 | Sent to Photo Copy |
Oct 23, 2014 | Permit Approved |
Nov 03, 2014 | Land Evidence Date |