Action Date | Action Description |
---|---|
Feb 13, 2013 | Assent Application Received |
Feb 13, 2013 | Administrative Review for Completeness |
Feb 13, 2013 | Team Review for Completeness |
Feb 13, 2013 | Application Accepted |
Feb 17, 2013 | HPHC Historical Preservation No Effect |
Mar 13, 2013 | Joint Public Notice |
Apr 05, 2013 | Additional Information Received |
Apr 13, 2013 | Public Notice End Date |
Apr 30, 2013 | Plans Received |
May 07, 2013 | Additional Information Received |
May 21, 2013 | Engineering Report |
May 21, 2013 | Biologist Report |
May 21, 2013 | Engineering Report |
May 23, 2013 | Mail Agenda Notice |
May 23, 2013 | Executive Signoff of Staff Reports |
May 28, 2013 | Semi-Monthly Meeting Date Scheduled |
May 28, 2013 | Water Quality Certification |
May 28, 2013 | Council Approval Granted |
May 28, 2013 | Semi-Monthly Meeting Held |
May 30, 2013 | Stipulation Package from Biologist |
Jun 05, 2013 | Stipulation Package by Engineer |
Jun 25, 2013 | Legal Response/Decision |
Jun 25, 2013 | US Army Corps of Engineers Approval Received |
Jun 25, 2013 | Under Review/Decision |
Jun 25, 2013 | 30 Day Appeal Notification to Owner |
Jun 26, 2013 | Permit Approved |
Jun 26, 2013 | Typist for Processing |
Jun 27, 2013 | Executive Sign Off |
Jun 27, 2013 | Sent to Photo Copy |
Jul 25, 2013 | US Army Corps of Engineers Approval Received |