Action Date | Action Description |
---|---|
Apr 09, 2013 | Assent Application Received |
Apr 10, 2013 | Administrative Review for Completeness |
Apr 11, 2013 | Team Review for Completeness |
Apr 11, 2013 | Team Review for Completeness |
Apr 11, 2013 | Application Accepted |
Jun 04, 2013 | Additional Information Received |
Jun 10, 2013 | HPHC Historical Preservation No Effect |
Jun 11, 2013 | Biologist Report |
Jun 11, 2013 | Sent to Photo Copy |
Jun 13, 2013 | Permit Approved |
Jun 13, 2013 | Typist for Processing |
Jun 14, 2013 | Executive Sign Off |
Jun 14, 2013 | Engineering Report |
Jun 21, 2013 | Land Evidence Date |