Action Date | Action Description |
---|---|
May 21, 2013 | Assent Application Received |
May 22, 2013 | Administrative Review for Completeness |
May 22, 2013 | Team Review for Completeness |
May 22, 2013 | Team Review for Completeness |
May 23, 2013 | Deficient Application - Owner Notification Sent |
Sep 27, 2013 | Deficiency Response Received |
Sep 27, 2013 | Team Review for Completeness |
Sep 27, 2013 | Team Review for Completeness |
Sep 27, 2013 | Application Accepted |
Oct 01, 2013 | 30 day Public Notice Issued |
Oct 04, 2013 | HPHC Historical Preservation No Effect |
Nov 01, 2013 | Public Notice End Date Extension Granted |
Nov 01, 2013 | Public Notice End Date |
Nov 12, 2013 | Correspondence Received |
Dec 04, 2013 | Biologist Report |
Dec 05, 2013 | Typist for Processing |
Dec 05, 2013 | Permit Approved |
Dec 06, 2013 | Executive Sign Off |
Dec 06, 2013 | Sent to Photo Copy |
Dec 09, 2013 | US Army Corps of Engineers Approval Received |
Mar 12, 2014 | Land Evidence Date |