Action Date | Action Description |
---|---|
Sep 17, 2013 | Assent Application Received |
Sep 18, 2013 | Administrative Review for Completeness |
Sep 27, 2013 | Team Review for Completeness |
Sep 27, 2013 | Application Accepted |
Oct 07, 2013 | 30 day Public Notice Issued |
Oct 17, 2013 | Additional Information Received |
Oct 18, 2013 | Additional Information Received |
Nov 01, 2013 | Public Notice End Date Extension Granted |
Nov 05, 2013 | HPHC Historical Preservation No Effect |
Nov 07, 2013 | Public Notice End Date |
Nov 12, 2013 | Correspondence Received |
Mar 21, 2014 | Plans Received |
Apr 10, 2014 | Plans Received |
Apr 23, 2014 | Plans Received |
Apr 25, 2014 | Biologist Report |
Apr 25, 2014 | Engineering Report |
May 08, 2014 | Permit Approved |
May 13, 2014 | Typist for Processing |
May 13, 2014 | Executive Sign Off |
May 13, 2014 | Sent to Photo Copy |
Sep 03, 2014 | Land Evidence Date |