Action Date | Action Description |
---|---|
Sep 30, 2013 | Assent Application Received |
Oct 01, 2013 | Administrative Review for Completeness |
Dec 03, 2013 | HPHC Historical Preservation No Effect |
Dec 13, 2013 | Team Review for Completeness |
Dec 13, 2013 | Application Accepted |
Jul 11, 2014 | 30 day Public Notice Issued |
Aug 11, 2014 | Public Notice End Date |
Aug 21, 2014 | Engineering Report |
Sep 03, 2014 | Permit Approved |
Sep 03, 2014 | Typist for Processing |
Sep 04, 2014 | Executive Sign Off |
Sep 04, 2014 | Sent to Photo Copy |
Jan 14, 2015 | Land Evidence Date |