Action Date | Action Description |
---|---|
May 28, 2014 | Assent Application Received |
May 28, 2014 | Administrative Review for Completeness |
May 29, 2014 | Team Review for Completeness |
May 29, 2014 | Application Accepted |
Jun 10, 2014 | HPHC Historical Preservation No Effect |
Dec 12, 2014 | Plans Received |
Dec 24, 2014 | Plans Received |
Jan 14, 2015 | Plans Received |
Feb 03, 2015 | Typist for Processing |
Feb 03, 2015 | Permit Approved |
Feb 03, 2015 | Engineering Report |
Feb 03, 2015 | Biologist Report |
Feb 09, 2015 | Executive Sign Off |
Feb 09, 2015 | Sent to Photo Copy |
Feb 23, 2015 | Land Evidence Date |
Aug 08, 2018 | Expiration of Assent/End of Tolling Legislation |