Action Date | Action Description |
---|---|
Jul 21, 2014 | Assent Application Received |
Jul 21, 2014 | Administrative Review for Completeness |
Jul 22, 2014 | Team Review for Completeness |
Jul 22, 2014 | Application Accepted |
Jul 30, 2014 | Historical Preservation Conditional Approval |
Aug 20, 2014 | HPHC Historical Preservation No Effect |
Aug 25, 2014 | HPHC Historical Preservation No Effect |
Aug 26, 2014 | Biologist Report |
Aug 27, 2014 | Typist for Processing |
Aug 27, 2014 | Permit Approved |
Aug 27, 2014 | Land Evidence Date |
Aug 28, 2014 | Executive Sign Off |