Action Date | Action Description |
---|---|
Jul 23, 2015 | Assent Application Received |
Jul 24, 2015 | Administrative Review for Completeness |
Aug 17, 2015 | Team Review for Completeness |
Aug 17, 2015 | Team Review for Completeness |
Aug 17, 2015 | Application Accepted |
Sep 16, 2015 | Plans Received |
Sep 21, 2015 | 30 day Public Notice Issued |
Nov 23, 2015 | Additional Information Requested from Applicant |
Jan 13, 2016 | Correspondence Received |
Jan 15, 2016 | Plans Received |
Feb 17, 2016 | Biologist Report |
Feb 22, 2016 | Additional Information Received |
Feb 29, 2016 | Engineering Report |
Mar 01, 2016 | Typist for Processing |
Mar 01, 2016 | Executive Sign Off |
Mar 01, 2016 | Sent to Photo Copy |
Mar 01, 2016 | Permit Approved |
Mar 05, 2018 | Modification Request |
Mar 05, 2018 | Administrative Review for Completeness |
Mar 12, 2018 | Team Review for Completeness |
Mar 12, 2018 | Deficient Application - Owner Notification Sent |
Mar 27, 2018 | Deficiency Response Received |
Apr 03, 2018 | Team Review for Completeness |
Apr 03, 2018 | Application Accepted |
Apr 11, 2018 | HPHC Historical Preservation No Effect |
May 04, 2018 | Additional Information Requested from Applicant |
Jun 08, 2018 | Additional Information Requested from Applicant |
Jul 03, 2018 | Correspondence Mailed/Faxed/E-mailed |
Aug 28, 2018 | 30-Day Notification of Cancellation letter |
Aug 31, 2018 | Note to File |
Sep 17, 2018 | Note to File |
Jan 24, 2019 | Additional Information Received |
Feb 19, 2019 | Plans Received |
Mar 04, 2019 | Biologist Report |
Mar 05, 2019 | Engineering Report |
Mar 05, 2019 | Typist for Processing |
Mar 05, 2019 | Executive Sign Off |
Mar 05, 2019 | Sent to Photo Copy |
Mar 05, 2019 | Modification Approved |
Mar 05, 2019 | Permit Approved |
Mar 06, 2019 | Land Evidence Date |