Action Date | Action Description |
---|---|
Aug 21, 2015 | Assent Application Received |
Aug 26, 2015 | Administrative Review for Completeness |
Sep 01, 2015 | Team Review for Completeness |
Sep 02, 2015 | Application Accepted |
Sep 24, 2015 | HPHC Historical Preservation No Effect |
Sep 29, 2015 | 30 day Public Notice Issued |
Oct 15, 2015 | US Army Corps of Engineers Approval Received |
Oct 30, 2015 | Public Notice End Date |
Dec 30, 2015 | Category A* (Docks) |
Apr 20, 2016 | Plans Received |
Jun 10, 2016 | Plans Received |
Aug 31, 2016 | Plans Received |
Sep 01, 2016 | Plans Received |
Sep 26, 2016 | Mail Agenda Notice |
Sep 29, 2016 | Biologist Report |
Oct 06, 2016 | Continuance Requested |
Oct 11, 2016 | Management Review |
Oct 11, 2016 | Continuance request by objector granted by Director |
Oct 11, 2016 | Semi-Monthly Meeting Date Scheduled |
Oct 14, 2016 | Ready to Schedule Semi-Monthly Meeting |
Oct 14, 2016 | Mail Agenda Notice |
Oct 25, 2016 | Semi-Monthly Meeting Date Scheduled |
Nov 09, 2016 | US Army Corps of Engineers Approval Received |
Dec 13, 2016 | Stipulation Package from Biologist |
Dec 16, 2016 | Typist for Processing |
Dec 16, 2016 | Executive Sign Off |
Dec 16, 2016 | Sent to Photo Copy |
Dec 16, 2016 | Legal Response/Decision |
Dec 16, 2016 | Permit Approved |
Dec 30, 2016 | Land Evidence Date |