Action Date | Action Description |
---|---|
Sep 28, 2015 | Assent Application Received |
Sep 29, 2015 | Administrative Review for Completeness |
Sep 29, 2015 | Team Review for Completeness |
Oct 06, 2015 | Application Accepted |
Oct 06, 2015 | HPHC Historical Preservation No Effect |
Oct 08, 2015 | 30 day Public Notice Issued |
Oct 21, 2015 | Objections/Comments Received |
Oct 29, 2015 | Plans Received |
Nov 08, 2015 | Public Notice End Date |
Nov 30, 2015 | Public Notice End Date Extension Granted |
Dec 01, 2015 | Biologist Report |
Dec 05, 2015 | Typist for Processing |
Dec 08, 2015 | US Army Corps of Engineers Approval Received |
Dec 09, 2015 | Category A* (Docks) |
Dec 09, 2015 | Executive Sign Off |
Dec 09, 2015 | Sent to Photo Copy |
Dec 09, 2015 | Permit Approved |
Dec 17, 2015 | Additional Information Received |
Dec 21, 2015 | Public Notice End Date Extension Granted |
Feb 02, 2016 | Correspondence Received |
Aug 03, 2016 | Land Evidence Date |