Action Date | Action Description |
---|---|
Dec 10, 2015 | Assent Application Received |
Dec 15, 2015 | Administrative Review for Completeness |
Dec 16, 2015 | Team Review for Completeness |
Dec 16, 2015 | Application Accepted |
Dec 23, 2015 | Additional Information Received |
Jan 15, 2016 | Biologist Report |
Jan 22, 2016 | Typist for Processing |
Jan 25, 2016 | Executive Sign Off |
Jan 25, 2016 | Sent to Photo Copy |
Jan 25, 2016 | Land Evidence Date |
Jan 25, 2016 | Permit Approved |
Jan 26, 2016 | HPHC Historical Preservation No Effect |