Action Date |
Action Description |
Sep 07, 2018 |
Assent Application Received |
Sep 10, 2018 |
Administrative Review for Completeness |
Sep 14, 2018 |
Team Review for Completeness |
Sep 27, 2018 |
Objections/Comments Received |
Sep 28, 2018 |
Application Accepted |
Sep 28, 2018 |
Team Review for Completeness |
Sep 28, 2018 |
Team Review for Completeness |
Oct 11, 2018 |
30 day Public Notice Issued |
Oct 16, 2018 |
Objections/Comments Received |
Oct 17, 2018 |
Objections/Comments Received |
Oct 17, 2018 |
Comments Received |
Oct 18, 2018 |
Objections/Comments Received |
Oct 18, 2018 |
HPHC Historical Preservation No Effect |
Oct 19, 2018 |
Objections/Comments Received |
Oct 22, 2018 |
Objections/Comments Received |
Oct 23, 2018 |
Objections/Comments Received |
Oct 25, 2018 |
Objections/Comments Received |
Oct 26, 2018 |
Additional Information Received |
Oct 31, 2018 |
Objections/Comments Received |
Nov 05, 2018 |
Objections/Comments Received |
Nov 06, 2018 |
Objections/Comments Received |
Nov 07, 2018 |
Objections/Comments Received |
Nov 08, 2018 |
Objections/Comments Received |
Nov 08, 2018 |
Objections/Comments Received |
Nov 09, 2018 |
Objections/Comments Received |
Nov 09, 2018 |
Objections/Comments Received |
Nov 10, 2018 |
Objections/Comments Received |
Nov 11, 2018 |
Public Notice End Date |
Nov 14, 2018 |
Additional Information Received |
Dec 07, 2018 |
Additional Information Received |
Jan 08, 2019 |
Additional Information Received |
Apr 22, 2019 |
Engineering Report |
Apr 24, 2019 |
Special Exception Public Hearing Notice mailed |
Apr 30, 2019 |
Biologist Report |
May 06, 2019 |
Additional Information Received |
May 09, 2019 |
Executive Signoff of Staff Reports |
May 14, 2019 |
Council Approval Granted |
May 14, 2019 |
Semi-Monthly Meeting Date Scheduled |
Jul 03, 2019 |
Correspondence Received |
Jul 17, 2019 |
Stipulation Package from Biologist |
Jul 17, 2019 |
Stipulation Package by Engineer |
Jul 18, 2019 |
Legal Response/Decision |
Jul 18, 2019 |
Typist for Processing |
Jul 18, 2019 |
Executive Sign Off |
Jul 18, 2019 |
Sent to Photo Copy |
Jul 18, 2019 |
Permit Approved |
Jul 24, 2019 |
Land Evidence Date |
Dec 11, 2019 |
Monitoring Report |
Dec 12, 2019 |
Monitoring Report |
Dec 16, 2019 |
Monitoring Report |
Dec 16, 2019 |
Correspondence Received |
Dec 19, 2019 |
Monitoring Report |
Dec 20, 2019 |
Monitoring Report |
Dec 24, 2019 |
Monitoring Report |
Dec 30, 2019 |
Monitoring Report |
Jan 07, 2020 |
Correspondence Received |
Jan 10, 2020 |
Monitoring Report |
Jan 27, 2020 |
Monitoring Report |
Jun 22, 2020 |
Modification Request |
Jun 22, 2020 |
Administrative Review for Completeness |
Jun 25, 2020 |
Eng Team Review for Completeness |
Jun 25, 2020 |
Project Manager |
Jul 08, 2020 |
HPHC Historical Preservation No Effect |
Jul 08, 2020 |
HPHC Review Pending |
Jul 16, 2020 |
Typist for Processing |
Jul 16, 2020 |
Modification Approved |
Jul 16, 2020 |
Engineering Report |
Aug 11, 2020 |
Land Evidence Date |
Jul 17, 2022 |
Assent Expiration Date |