Action Date | Action Description |
---|---|
Assent Requirement | |
Sep 10, 2018 | Assent Application Received |
Sep 10, 2018 | Administrative Review for Completeness |
Sep 14, 2018 | Team Review for Completeness |
Oct 02, 2018 | Additional Information Received |
Oct 09, 2018 | Application Accepted |
Oct 09, 2018 | Team Review for Completeness |
Oct 30, 2018 | HPHC Historical Preservation No Effect |
Nov 14, 2018 | Biologist Report |
Nov 16, 2018 | Typist for Processing |
Nov 16, 2018 | Executive Sign Off |
Nov 16, 2018 | Sent to Photo Copy |
Nov 16, 2018 | Permit Approved |
Feb 04, 2019 | Land Evidence Date |
Mar 11, 2021 | Correspondence Mailed/Faxed/E-mailed |
May 10, 2021 | Correspondence Received |
May 10, 2021 | Correspondence Mailed/Faxed/E-mailed |