Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Enforcement Compliance Inspection Required | |
May 22, 2019 | Assent Application Received |
May 22, 2019 | Administrative Review for Completeness |
Jun 10, 2019 | Team Review for Completeness |
Jun 10, 2019 | Application Accepted |
Jun 10, 2019 | 30 day Public Notice Issued |
Jun 10, 2019 | Category A* (Docks) |
Jun 24, 2019 | HPHC Review Pending |
Jun 24, 2019 | HPHC Historical Preservation No Effect |
Jul 10, 2019 | Public Notice End Date |
Jul 29, 2019 | Dock/1.1.6 Review approval |
Aug 06, 2019 | Engineering Report |
Aug 06, 2019 | Typist for Processing |
Aug 06, 2019 | Executive Sign Off |
Aug 06, 2019 | Sent to Photo Copy |
Aug 06, 2019 | Permit Approved |
Aug 28, 2019 | Land Evidence Date |
May 18, 2022 | Extension of Permit Request |
Oct 25, 2022 | Enforcement Compliance Inspection Required |
Oct 25, 2022 | Process Extension |
Oct 25, 2022 | Extension Approved |
Jun 28, 2023 | Extension of Permit Request |
Aug 07, 2023 | Enforcement Compliance Inspection Required |
Aug 08, 2023 | Process Extension |
Aug 08, 2023 | Extension Approved |
Jul 23, 2024 | Extension of Permit Request |