Action Date | Action Description |
---|---|
Feb 20, 2020 | Assent Application Received |
Feb 20, 2020 | Administrative Review for Completeness |
Feb 21, 2020 | Bio Team Review for Completeness |
Feb 21, 2020 | Application Accepted |
Feb 25, 2020 | HPHC Review Pending |
Feb 25, 2020 | HPHC Historical Preservation No Effect |
Mar 06, 2020 | Project Manager |
Jun 04, 2020 | Plans Received |
Aug 17, 2020 | Additional Information Received |
May 05, 2021 | Additional Information Received |
May 20, 2021 | Stipulation Package from Biologist |
May 20, 2021 | Biologist Report |
May 24, 2021 | Executive Sign Off |
May 24, 2021 | Engineering Report |
May 24, 2021 | Stipulation Package by Engineer |
May 24, 2021 | Typist for Processing |
May 24, 2021 | Permit Approved |
Aug 11, 2021 | Land Evidence Date |