Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Jan 13, 2021 | Assent Application Received |
Jan 15, 2021 | Administrative Review for Completeness |
Jan 21, 2021 | Bio Team Review for Completeness |
Jan 21, 2021 | Application Accepted |
Jan 22, 2021 | Project Manager |
Jan 22, 2021 | Category B assigned |
Feb 17, 2021 | HPHC Historical Preservation No Effect |
Feb 17, 2021 | HPHC Review Pending |
Mar 04, 2021 | US Army Corps of Engineers Approval Received |
Apr 08, 2021 | 30 day Public Notice Issued |
May 08, 2021 | Public Notice End Date |
Jun 24, 2021 | Biologist Report |
Jun 24, 2021 | Stipulation Package from Biologist |
Jun 25, 2021 | Executive Sign Off |
Jun 25, 2021 | Sent to Photo Copy |
Jun 25, 2021 | Permit Approved |
Jun 25, 2021 | Typist for Processing |
Jul 09, 2021 | Land Evidence Date |