Action Date | Action Description |
---|---|
Land Evidence Date | |
May 18, 2022 | Assent Application Received |
May 18, 2022 | CHA Worksheet received |
May 19, 2022 | Administrative Review for Completeness |
May 20, 2022 | Bio Team Review for Completeness |
May 20, 2022 | Application Accepted |
May 23, 2022 | Project Manager |
Jun 13, 2022 | HPHC Historical Preservation No Effect |
Jun 13, 2022 | HPHC Review Pending |
Jun 29, 2022 | Biologist Report |
Jul 08, 2022 | Typist for Processing |
Jul 08, 2022 | Executive Sign Off |
Jul 08, 2022 | Sent to Photo Copy |
Jul 08, 2022 | Permit Approved |
Jul 08, 2022 | Permit Mailed |
Jan 10, 2023 | Land Evidence Date |
Aug 02, 2023 | Modification Request |
Aug 04, 2023 | Administrative Review for Completeness |
Aug 08, 2023 | Bio Team Review for Completeness |
Aug 08, 2023 | Project Manager |
Aug 17, 2023 | HPHC Historical Preservation No Effect |
Aug 23, 2023 | Biologist Report |
Aug 28, 2023 | Typist for Processing |
Aug 28, 2023 | Executive Sign Off |
Aug 28, 2023 | Sent to Photo Copy |
Aug 30, 2023 | Modification Approved |
Sep 11, 2023 | HPHC Historical Preservation No Effect |
Jul 12, 2024 | Modification Request |
Jul 19, 2024 | Administrative Review for Completeness |
Jul 23, 2024 | Bio Team Review for Completeness |
Jul 23, 2024 | Project Manager |
Jul 24, 2024 | Biologist Report |
Jul 24, 2024 | Additional Information Received |
Jul 26, 2024 | HPHC Historical Preservation No Effect |
Aug 14, 2024 | Typist for Processing |
Aug 19, 2024 | Executive Sign Off |
Aug 19, 2024 | Sent to Photo Copy |
Aug 19, 2024 | Permit Mailed |