Action Date | Action Description |
---|---|
Feb 01, 2024 | Maintenance Certification Request |
Feb 07, 2024 | Administrative Review for Completeness |
Mar 01, 2024 | Geologist Report |
Mar 01, 2024 | Deficient Application - Owner Notification Sent |
Mar 11, 2024 | Deficiency Response Received |
Mar 19, 2024 | Team Review for Completeness |
Mar 19, 2024 | Application Accepted |
Mar 19, 2024 | Project Manager |
Aug 20, 2024 | Additional Information Received |
Oct 25, 2024 | Typist for Processing |
Oct 25, 2024 | Executive Sign Off |
Oct 25, 2024 | Sent to Photo Copy |
Oct 25, 2024 | Permit Approved |
Oct 25, 2024 | Geologist Report |
Oct 29, 2024 | Permit Mailed |
Nov 07, 2024 | Commencement of Work Notice received |