Action Date | Action Description |
---|---|
Land Evidence Date | |
Jul 23, 2024 | Assent Application Received |
Jul 30, 2024 | Administrative Review for Completeness |
Aug 19, 2024 | Eng Team Review for Completeness |
Aug 19, 2024 | Bio Team Review for Completeness |
Aug 19, 2024 | Project Manager |
Aug 19, 2024 | Application Accepted |
Aug 30, 2024 | HPHC Historical Preservation No Effect |
Oct 16, 2024 | Engineering Report |
Nov 15, 2024 | Typist for Processing |
Nov 15, 2024 | Executive Sign Off |
Nov 15, 2024 | Sent to Photo Copy |
Nov 15, 2024 | Permit Approved |
Nov 21, 2024 | Permit Mailed |