Action Date | Action Description |
---|---|
Mar 05, 2004 | Application Accepted |
Mar 17, 2004 | Historical Preservation Approval Granted |
Jun 01, 2004 | Biologist Report |
Jun 01, 2004 | Engineering Report |
Jun 03, 2004 | Permit Approved |
Jun 03, 2004 | Land Evidence Date |
Jun 30, 2004 | Correspondence Received |
Dec 22, 2004 | Modification Request |
Dec 23, 2004 | Administrative Review for Completeness |
Mar 01, 2005 | Plans Received |
Mar 10, 2005 | Team Review for Completeness |
Apr 15, 2005 | Historical Preservation Approval Granted |
May 24, 2005 | Engineering Report |
May 25, 2005 | Typist for Processing |
May 25, 2005 | Modification Approved |
May 26, 2005 | Executive Sign Off |
May 26, 2005 | Sent to Photo Copy |
Jul 21, 2005 | Assent Correction Mailed |
Jul 22, 2005 | Land Evidence Date |