Action Date | Action Description |
---|---|
Feb 24, 2005 | Assent Application Received |
Feb 25, 2005 | Administrative Review for Completeness |
Feb 25, 2005 | Deficient Application - Owner Notification Sent |
Mar 09, 2005 | Deficient Application Picked Up |
May 26, 2005 | Deficiency Response Received |
May 26, 2005 | Team Review for Completeness |
May 26, 2005 | Application Accepted |
May 26, 2005 | Category A* (Docks) |
Jun 01, 2005 | 30 day Public Notice Issued |
Jun 10, 2005 | HPHC Review Pending |
Jul 13, 2005 | Engineering Report |
Aug 05, 2005 | Correspondence Received |
Aug 05, 2005 | Correspondence Received |
Aug 08, 2005 | Public Notice End Date |
Aug 11, 2005 | Executive Sign Off |
Aug 11, 2005 | Biologist Report |
Aug 18, 2005 | Ready to Schedule Semi-Monthly Meeting |
Aug 18, 2005 | Mail Agenda Notice |
Aug 23, 2005 | Semi-Monthly Meeting Held |
Aug 23, 2005 | Semi-Monthly Meeting Date Scheduled |
Aug 23, 2005 | Remanded back to staff by Council |
Dec 13, 2005 | Correspondence Mailed/Faxed/E-mailed |
Dec 23, 2005 | Plans Received |
Dec 27, 2005 | Supervisor Biologist SignOff |
Dec 27, 2005 | Supervisor Engineer SignOff |
Jan 03, 2006 | Executive Sign Off |
Jan 12, 2006 | Mail Agenda Notice |
Jan 12, 2006 | Ready to Schedule Semi-Monthly Meeting |
Jan 24, 2006 | Semi-Monthly Meeting Held |
Jan 24, 2006 | Council Approval Granted |
Jan 24, 2006 | Semi-Monthly Meeting Date Scheduled |
Jan 31, 2006 | Legal Response/Decision |
Sep 25, 2006 | Stipulation Package from Biologist |
Sep 25, 2006 | Stipulation Package by Engineer |
Oct 16, 2006 | Correspondence Mailed/Faxed/E-mailed |
Oct 18, 2006 | Plans Received |
Oct 30, 2006 | Typist for Processing |
Oct 30, 2006 | Executive Sign Off |
Oct 30, 2006 | Sent to Photo Copy |
Oct 30, 2006 | Permit Approved |
Nov 27, 2006 | Land Evidence Date |
Jan 31, 2007 | Under Review/Decision |
Jul 09, 2009 | Extension of Permit Request |
Jul 23, 2009 | Enforcement Compliance Inspection Required |
Jul 23, 2009 | Extension Approved |