Action Date | Action Description |
---|---|
Apr 29, 2005 | Assent Application Received |
May 02, 2005 | Administrative Review for Completeness |
May 03, 2005 | Team Review for Completeness |
May 03, 2005 | Application Accepted |
May 03, 2005 | Category B assigned |
May 20, 2005 | Historical Preservation Approval Granted |
May 27, 2005 | HPHC Review Pending |
Jun 08, 2005 | 30 day Public Notice Issued |
Jul 08, 2005 | Public Notice End Date |
Sep 14, 2005 | 30 day Public Notice Issued |
Oct 14, 2005 | Public Notice End Date |
Oct 19, 2005 | Biologist Report |
Oct 19, 2005 | Engineering Report |
Oct 25, 2005 | Correspondence Received |
Oct 28, 2005 | Supervisor Biologist SignOff |
Oct 28, 2005 | Supervisor Engineer SignOff |
Nov 01, 2005 | Executive Sign Off |
Nov 04, 2005 | Ready to Schedule Semi-Monthly Meeting |
Nov 04, 2005 | Mail Agenda Notice |
Nov 08, 2005 | Continued Application by the Council |
Nov 08, 2005 | Semi-Monthly Meeting Date Scheduled |
Nov 16, 2005 | Mail Agenda Notice |
Nov 22, 2005 | Semi-Monthly Meeting Held |
Nov 22, 2005 | Council Approval Granted |
Nov 22, 2005 | Semi-Monthly Meeting Date Scheduled |
Nov 25, 2005 | Stipulation Package from Biologist |
Nov 25, 2005 | Stipulation Package by Engineer |
Nov 28, 2005 | Permit Approved |
Nov 28, 2005 | Typist for Processing |
Nov 28, 2005 | Executive Sign Off |
Nov 28, 2005 | Sent to Photo Copy |
Nov 29, 2005 | Legal Response/Decision |
Nov 30, 2005 | Under Review/Decision |
Jan 23, 2006 | Land Evidence Date |