Action Date | Action Description |
---|---|
Aug 10, 2007 | Assent Application Received |
Aug 14, 2007 | Administrative Review for Completeness |
Aug 14, 2007 | Team Review for Completeness |
Aug 14, 2007 | Team Review for Completeness |
Aug 14, 2007 | Application Accepted |
Aug 14, 2007 | Category B assigned |
Aug 17, 2007 | 30 day Public Notice Issued |
Aug 24, 2007 | HPHC Historical Preservation No Effect |
Sep 16, 2007 | Public Notice End Date |
Jan 29, 2008 | Plans Received |
Feb 01, 2008 | Plans Received |
Mar 11, 2008 | Plans Received |
Mar 28, 2008 | Plans Received |
Mar 28, 2008 | Biologist Report |
Mar 28, 2008 | Engineering Report |
Apr 03, 2008 | Supervisor Biologist SignOff |
Apr 04, 2008 | Supervisor Engineer SignOff |
Apr 08, 2008 | Executive Signoff of Staff Reports |
May 02, 2008 | Ready to Schedule Semi-Monthly Meeting |
May 02, 2008 | Mail Agenda Notice |
May 13, 2008 | Continued Application by the Council |
May 13, 2008 | Semi-Monthly Meeting Date Scheduled |
May 19, 2008 | Ready to Schedule Semi-Monthly Meeting |
May 19, 2008 | Mail Agenda Notice |
May 27, 2008 | Semi-Monthly Meeting Held |
May 27, 2008 | Council Approval Granted |
May 27, 2008 | Semi-Monthly Meeting Date Scheduled |
May 28, 2008 | Stipulation Package from Biologist |
May 28, 2008 | Stipulation Package by Engineer |
May 28, 2008 | Typist for Processing |
May 28, 2008 | Executive Sign Off |
May 28, 2008 | Sent to Photo Copy |
May 28, 2008 | Permit Approved |
Aug 04, 2009 | Legal Response/Decision |