Action Date | Action Description |
---|---|
Feb 21, 2008 | Assent Application Received |
Feb 22, 2008 | Administrative Review for Completeness |
Feb 22, 2008 | Team Review for Completeness |
Feb 22, 2008 | Team Review for Completeness |
Feb 22, 2008 | Application Accepted |
Mar 18, 2008 | HPHC Historical Preservation No Effect |
Apr 21, 2008 | Additional Information Received |
Apr 25, 2008 | Additional Information Received |
Apr 25, 2008 | Typist for Processing |
Apr 25, 2008 | Executive Sign Off |
Apr 25, 2008 | Sent to Photo Copy |
Apr 25, 2008 | Permit Approved |
Apr 25, 2008 | Biologist Report |
Apr 25, 2008 | Engineering Report |
May 02, 2008 | Land Evidence Date |
May 02, 2008 | Commencement of Work Notice received |
Jun 20, 2008 | Modification Request |
Jun 25, 2008 | Administrative Review for Completeness |
Jun 25, 2008 | Team Review for Completeness |
Jun 25, 2008 | Team Review for Completeness |
Jun 27, 2008 | Biologist Report |
Jun 27, 2008 | Engineering Report |
Jun 27, 2008 | Typist for Processing |
Jun 27, 2008 | Modification Approved |
Jul 03, 2008 | Land Evidence Date |
Jul 03, 2008 | Executive Sign Off |
Jul 03, 2008 | Sent to Photo Copy |