Action Date | Action Description |
---|---|
Aug 27, 2009 | Maintenance Certification Request |
Aug 28, 2009 | Administrative Review for Completeness |
Aug 31, 2009 | Team Review for Completeness |
Aug 31, 2009 | Team Review for Completeness |
Aug 31, 2009 | Application Accepted |
Aug 31, 2009 | Category A* (Docks) |
Sep 02, 2009 | Additional Information Received |
Sep 08, 2009 | 30 day Public Notice Issued |
Sep 11, 2009 | HPHC Historical Preservation No Effect |
Sep 14, 2009 | Correspondence Received |
Sep 16, 2009 | Entry of Appearance Received |
Oct 08, 2009 | Public Notice End Date |
Nov 09, 2009 | Category A assigned |
Dec 24, 2009 | Additional Information Received |
Dec 28, 2009 | Engineering Report |
Jan 06, 2010 | Scheduled for Section 110 Review meeting |
Jan 06, 2010 | Dock/1.1.6 Review approval |
Jan 06, 2010 | Biologist Report |
Jan 07, 2010 | Typist for Processing |
Jan 07, 2010 | Permit Approved |
Jan 29, 2010 | Land Evidence Date |
Feb 11, 2010 | Commencement of Work Notice received |