Action Date | Action Description |
---|---|
Sep 16, 2009 | Assent Application Received |
Sep 16, 2009 | Administrative Review for Completeness |
Sep 18, 2009 | Team Review for Completeness |
Sep 18, 2009 | Team Review for Completeness |
Sep 18, 2009 | Application Accepted |
Sep 18, 2009 | Category A* (Docks) |
Sep 22, 2009 | 30 day Public Notice Issued |
Oct 09, 2009 | Plans Received |
Oct 09, 2009 | HPHC Historical Preservation No Effect |
Oct 22, 2009 | Public Notice End Date |
Nov 19, 2009 | Engineering Report |
Nov 23, 2009 | Biologist Report |
Nov 23, 2009 | Typist for Processing |
Nov 23, 2009 | Executive Sign Off |
Nov 23, 2009 | Sent to Photo Copy |
Nov 23, 2009 | Permit Approved |
Dec 17, 2009 | Land Evidence Date |
Dec 23, 2009 | US Army Corps of Engineers Approval Received |
Jun 08, 2010 | Commencement of Work Notice received |