Action Date | Action Description |
---|---|
Sep 21, 2009 | Assent Application Received |
Sep 22, 2009 | Administrative Review for Completeness |
Sep 30, 2009 | Team Review for Completeness |
Sep 30, 2009 | Team Review for Completeness |
Sep 30, 2009 | Application Accepted |
Oct 01, 2009 | Biologist Report |
Oct 01, 2009 | Engineering Report |
Oct 01, 2009 | Typist for Processing |
Oct 08, 2009 | Permit Approved |
Oct 09, 2009 | Land Evidence Date |