Sep 24, 2009 | Dredge Application |
Sep 24, 2009 | Administrative Review for Completeness |
Sep 28, 2009 | Team Review for Completeness |
Sep 28, 2009 | Application Accepted |
Oct 16, 2009 | HPHC Historical Preservation No Effect |
Oct 26, 2009 | 30 day Public Notice Issued |
Nov 27, 2009 | Public Notice End Date |
Apr 14, 2010 | Additional Information Received |
Apr 19, 2010 | Biologist Report |
May 17, 2010 | Plans Received |
Jun 17, 2010 | US Army Corp of Engineers Permit Date |
Jun 25, 2010 | US Army Corps of Engineers Approval Received |
Jun 28, 2010 | Monitoring Report |
Jul 23, 2010 | Engineering Report |
Oct 08, 2010 | Water Quality Certification |
Oct 08, 2010 | Typist for Processing |
Oct 08, 2010 | Executive Sign Off |
Oct 08, 2010 | Sent to Photo Copy |
Oct 08, 2010 | Permit Approved |
Oct 26, 2010 | Land Evidence Date |
Jan 20, 2011 | Commencement of Work Notice received |
Feb 27, 2012 | Monitoring Report |
Dec 17, 2012 | Monitoring Report |
Dec 18, 2012 | Monitoring Report |
Nov 20, 2013 | Monitoring Report |
Jan 07, 2016 | Monitoring Report |