Jul 09, 2010 | Assent Application Received |
Jul 13, 2010 | Administrative Review for Completeness |
Jul 13, 2010 | Team Review for Completeness |
Jul 13, 2010 | Team Review for Completeness |
Jul 13, 2010 | Application Accepted |
Jul 26, 2010 | HPHC Historical Preservation No Effect |
Jul 28, 2010 | Additional Information Received |
Aug 05, 2010 | 30 day Public Notice Issued |
Sep 05, 2010 | Public Notice End Date |
Sep 24, 2010 | Biologist Report |
Sep 24, 2010 | Engineering Report |
Sep 29, 2010 | US Army Corp of Engineers Permit Date |
Oct 04, 2010 | Supervisor Biologist SignOff |
Oct 04, 2010 | Supervisor Engineer SignOff |
Oct 04, 2010 | Executive Signoff of Staff Reports |
Oct 15, 2010 | Ready to Schedule Semi-Monthly Meeting |
Oct 15, 2010 | Mail Agenda Notice |
Oct 26, 2010 | Semi-Monthly Meeting Held |
Oct 26, 2010 | Council Approval Granted |
Oct 26, 2010 | Semi-Monthly Meeting Date Scheduled |
Oct 27, 2010 | Stipulation Package from Biologist |
Oct 27, 2010 | Stipulation Package by Engineer |
Nov 05, 2010 | Permit Approved |
Nov 05, 2010 | Typist for Processing |
Nov 05, 2010 | Category A* (Docks) |
Nov 09, 2010 | Executive Sign Off |
Nov 09, 2010 | Sent to Photo Copy |
Nov 15, 2010 | Land Evidence Date |
Jun 01, 2011 | Commencement of Work Notice received |