Action Date | Action Description |
---|---|
Mar 01, 2012 | Assent Application Received |
Mar 01, 2012 | Administrative Review for Completeness |
Mar 02, 2012 | Team Review for Completeness |
Mar 02, 2012 | Team Review for Completeness |
Mar 02, 2012 | Application Accepted |
Mar 20, 2012 | Additional Information Received |
Mar 23, 2012 | Biologist Report |
Mar 23, 2012 | Engineering Report |
Mar 26, 2012 | Typist for Processing |
Mar 26, 2012 | Executive Sign Off |
Mar 26, 2012 | Sent to Photo Copy |
Mar 26, 2012 | Permit Approved |
Mar 27, 2012 | Land Evidence Date |
Apr 03, 2012 | HPHC Historical Preservation No Effect |
Apr 30, 2012 | Commencement of Work Notice received |