Action Date | Action Description |
---|---|
Mar 05, 2012 | Assent Application Received |
Mar 05, 2012 | Administrative Review for Completeness |
Mar 07, 2012 | Team Review for Completeness |
Mar 07, 2012 | Team Review for Completeness |
Mar 07, 2012 | Application Accepted |
Mar 27, 2012 | 30 day Public Notice Issued |
Apr 03, 2012 | HPHC Historical Preservation No Effect |
Apr 27, 2012 | Public Notice End Date |
Aug 03, 2012 | Geologist Report |
Aug 08, 2012 | Biologist Report |
Aug 08, 2012 | Engineering Report |
Aug 09, 2012 | Supervisor Biologist SignOff |
Aug 09, 2012 | Supervisor Engineer SignOff |
Aug 09, 2012 | Executive Signoff of Staff Reports |
Sep 04, 2012 | Ready to Schedule Semi-Monthly Meeting |
Sep 07, 2012 | Continuance Requested |
Sep 11, 2012 | Continuance request by applicant granted by Director |
Sep 11, 2012 | Semi-Monthly Meeting Date Scheduled |
Sep 11, 2012 | Mail Agenda Notice |
Sep 25, 2012 | Semi-Monthly Meeting Date Scheduled |
Sep 25, 2012 | Semi-Monthly Meeting Held |
May 03, 2013 | Additional Information Received |
May 09, 2013 | Dock/1.1.6 Review approval |
May 29, 2013 | Additional Information Received |
Jun 06, 2013 | Additional Information Received |
Jun 11, 2013 | Typist for Processing |
Jun 11, 2013 | Permit Approved |
Jun 14, 2013 | Executive Sign Off |
Jun 14, 2013 | Sent to Photo Copy |
Jul 12, 2013 | Assent Correction Mailed |
Jul 18, 2013 | Land Evidence Date |
Aug 13, 2013 | Land Evidence Date |