Action Date | Action Description |
---|---|
May 07, 2012 | Assent Application Received |
May 07, 2012 | Administrative Review for Completeness |
May 07, 2012 | Team Review for Completeness |
May 07, 2012 | Team Review for Completeness |
May 07, 2012 | Application Accepted |
May 11, 2012 | 30 day Public Notice Issued |
May 16, 2012 | HPHC Historical Preservation No Effect |
Jun 11, 2012 | Public Notice End Date |
Jun 15, 2012 | Biologist Report |
Jun 15, 2012 | Engineering Report |
Jun 19, 2012 | Supervisor Engineer SignOff |
Jun 20, 2012 | Executive Signoff of Staff Reports |
Jun 20, 2012 | Supervisor Biologist SignOff |
Jul 05, 2012 | US Army Corps of Engineers Approval Received |
Aug 10, 2012 | Ready to Schedule Semi-Monthly Meeting |
Aug 10, 2012 | Mail Agenda Notice |
Aug 28, 2012 | Council Approval Granted |
Aug 28, 2012 | Semi-Monthly Meeting Date Scheduled |
Aug 28, 2012 | Semi-Monthly Meeting Held |
Aug 30, 2012 | Stipulation Package from Biologist |
Aug 30, 2012 | Stipulation Package by Engineer |
Sep 10, 2012 | Legal Response/Decision |
Sep 19, 2012 | Typist for Processing |
Sep 19, 2012 | Permit Approved |
Sep 20, 2012 | Executive Sign Off |
Sep 20, 2012 | Sent to Photo Copy |
Sep 28, 2012 | Land Evidence Date |