Action Date | Action Description |
---|---|
Aug 09, 2012 | Assent Application Received |
Aug 09, 2012 | Administrative Review for Completeness |
Sep 17, 2012 | Team Review for Completeness |
Sep 17, 2012 | Additional Information Received |
Sep 17, 2012 | Application Accepted |
Sep 20, 2012 | Biologist Report |
Sep 21, 2012 | Typist for Processing |
Sep 21, 2012 | Permit Approved |
Sep 24, 2012 | Executive Sign Off |
Sep 24, 2012 | Sent to Photo Copy |