Action Date | Action Description |
---|---|
Oct 12, 2012 | Assent Application Received |
Oct 15, 2012 | Administrative Review for Completeness |
Dec 26, 2012 | Additional Information Received |
Jan 31, 2013 | Additional Information Received |
Apr 02, 2013 | 30 day Public Notice Issued |
Apr 02, 2013 | Application Accepted |
May 02, 2013 | Public Notice End Date |
May 09, 2013 | Biologist Report |
May 09, 2013 | Engineering Report |
May 17, 2013 | Typist for Processing |
May 17, 2013 | Permit Approved |
May 20, 2013 | Executive Sign Off |
May 20, 2013 | Sent to Photo Copy |
May 22, 2013 | Land Evidence Date |
Jun 03, 2013 | US Army Corps of Engineers Approval Received |