Action Date | Action Description |
---|---|
Nov 20, 2012 | Freshwater Wetland - Preliminary Determination |
Nov 20, 2012 | Administrative Review for Completeness |
Jan 09, 2013 | Team Review for Completeness |
Jan 09, 2013 | Team Review for Completeness |
Jan 09, 2013 | Application Accepted |
Feb 05, 2013 | Additional Information Received |
Feb 12, 2013 | Biologist Report |
Feb 12, 2013 | Engineering Report |
Feb 13, 2013 | Typist for Processing |
Feb 14, 2013 | Executive Sign Off |
Feb 14, 2013 | Sent to Photo Copy |
Feb 14, 2013 | Permit Approved |
Feb 22, 2013 | Land Evidence Date |