Action Date | Action Description |
---|---|
Dec 24, 2012 | Assent Application Received |
Dec 24, 2012 | Administrative Review for Completeness |
Jan 14, 2013 | Team Review for Completeness |
Jan 14, 2013 | Deficient Application - Owner Notification Sent |
Feb 07, 2013 | Deficient Application Picked Up |
Feb 07, 2013 | Deficiency Response Received |
Feb 08, 2013 | Team Review for Completeness |
Feb 13, 2013 | Application Accepted |
Feb 13, 2013 | Team Review for Completeness |
Feb 19, 2013 | HPHC Historical Preservation No Effect |
Feb 22, 2013 | Additional Information Received |
Mar 08, 2013 | Plans Received |
Mar 15, 2013 | Additional Information Received |
Mar 18, 2013 | Biologist Report |
Mar 26, 2013 | Typist for Processing |
Mar 26, 2013 | Permit Approved |
Mar 27, 2013 | Executive Sign Off |
Mar 27, 2013 | Sent to Photo Copy |
Apr 01, 2013 | Land Evidence Date |
Jun 28, 2013 | Additional Information Received |
Oct 01, 2014 | Modification Request |
Oct 06, 2014 | Administrative Review for Completeness |
Oct 08, 2014 | Team Review for Completeness |
Oct 21, 2014 | HPHC Historical Preservation No Effect |
Nov 03, 2014 | Biologist Report |
Nov 05, 2014 | Typist for Processing |
Nov 05, 2014 | Modification Approved |
Nov 07, 2014 | Executive Sign Off |
Nov 07, 2014 | Sent to Photo Copy |
Nov 19, 2014 | Land Evidence Date |