Action Date | Action Description |
---|---|
Apr 10, 2013 | Assent Application Received |
Apr 10, 2013 | Administrative Review for Completeness |
Apr 15, 2013 | Fee Waiver Granted |
Apr 19, 2013 | Team Review for Completeness |
Apr 19, 2013 | Application Accepted |
Apr 30, 2013 | HPHC Historical Preservation No Effect |
May 28, 2013 | Water Quality Certification |
Jul 10, 2013 | Biologist Report |
Jul 15, 2013 | Typist for Processing |
Jul 15, 2013 | Executive Sign Off |
Jul 15, 2013 | Sent to Photo Copy |
Jul 15, 2013 | Permit Approved |
Jul 25, 2013 | US Army Corps of Engineers Approval Received |
Dec 10, 2014 | Commencement of Work Notice received |
Dec 11, 2014 | Modification Request |
Dec 11, 2014 | Report completed |
Dec 12, 2014 | Policy Review |
Dec 12, 2014 | Correspondence Received |
Dec 18, 2014 | Typist for Processing |
Dec 18, 2014 | Executive Sign Off |
Dec 18, 2014 | Sent to Photo Copy |
Dec 18, 2014 | Modification Approved |