Action Date | Action Description |
---|---|
Jun 14, 2013 | Maintenance Certification Request |
Jun 17, 2013 | Administrative Review for Completeness |
Jun 21, 2013 | Team Review for Completeness |
Jul 12, 2013 | Team Review for Completeness |
Jul 15, 2013 | Team Review for Completeness |
Jul 15, 2013 | Application Accepted |
Aug 06, 2013 | HPHC Historical Preservation No Effect |
Oct 24, 2013 | Typist for Processing |
Oct 24, 2013 | Engineering Report |
Oct 24, 2013 | Permit Approved |
Oct 25, 2013 | Executive Sign Off |
Oct 25, 2013 | Sent to Photo Copy |