Action Date | Action Description |
---|---|
Aug 07, 2013 | Assent Application Received |
Aug 08, 2013 | Administrative Review for Completeness |
Aug 08, 2013 | Team Review for Completeness |
Aug 27, 2013 | Deficient Application - Owner Notification Sent |
Sep 05, 2013 | Deficiency Response Received |
Sep 12, 2013 | Team Review for Completeness |
Sep 12, 2013 | Application Accepted |
Sep 26, 2013 | HPHC Historical Preservation No Effect |
Sep 30, 2013 | 30 day Public Notice Issued |
Oct 30, 2013 | Public Notice End Date |
Nov 01, 2013 | Public Notice End Date Extension Granted |
Nov 12, 2013 | Correspondence Received |
Jan 31, 2014 | US Army Corps of Engineers Approval Received |
May 07, 2014 | Biologist Report |
May 15, 2014 | Typist for Processing |
May 15, 2014 | Permit Approved |
May 20, 2014 | Executive Sign Off |
May 20, 2014 | Sent to Photo Copy |
Jun 04, 2014 | Land Evidence Date |
Jul 14, 2014 | Correspondence Received |