Action Date | Action Description |
---|---|
Oct 01, 2013 | Maintenance Certification Request |
Oct 02, 2013 | Administrative Review for Completeness |
Oct 02, 2013 | Team Review for Completeness |
Oct 02, 2013 | Application Accepted |
Oct 09, 2013 | HPHC Historical Preservation No Effect |
Nov 19, 2013 | Engineering Report |
Nov 20, 2013 | Typist for Processing |
Nov 20, 2013 | Permit Approved |
Nov 22, 2013 | Executive Sign Off |
Nov 22, 2013 | Sent to Photo Copy |