Action Date | Action Description |
---|---|
Apr 02, 2018 | Assent Application Received |
Apr 02, 2018 | Administrative Review for Completeness |
Apr 03, 2018 | Team Review for Completeness |
Apr 03, 2018 | Application Accepted |
Apr 20, 2018 | HPHC Historical Preservation No Effect |
May 10, 2018 | Biologist Report |
May 11, 2018 | Typist for Processing |
May 11, 2018 | Executive Sign Off |
May 11, 2018 | Sent to Photo Copy |
May 11, 2018 | Permit Approved |
Aug 16, 2018 | Commencement of Work Notice received |
Aug 23, 2018 | Assent Requirement |