Action Date | Action Description |
---|---|
Assent Requirement | |
Feb 28, 2022 | Assent Application Received |
Mar 03, 2022 | Administrative Review for Completeness |
Mar 03, 2022 | CHA Worksheet received |
Mar 07, 2022 | Bio Team Review for Completeness |
Mar 07, 2022 | Application Accepted |
Mar 07, 2022 | Project Manager |
Mar 24, 2022 | HPHC Review Pending |
Mar 24, 2022 | HPHC Historical Preservation No Effect |
May 02, 2022 | Plans Received |
May 06, 2022 | Biologist Report |
May 10, 2022 | Typist for Processing |
May 12, 2022 | Permit Mailed |
May 12, 2022 | Executive Sign Off |
May 12, 2022 | Sent to Photo Copy |
May 12, 2022 | Permit Approved |
Jun 20, 2022 | Note to File |
Jun 21, 2022 | Land Evidence Date |
Apr 28, 2023 | Letter of Authorization |
May 02, 2023 | Modification Request |
May 08, 2023 | Administrative Review for Completeness |
May 09, 2023 | Bio Team Review for Completeness |
May 09, 2023 | Project Manager |
May 15, 2023 | Commencement of Work Notice received |
May 18, 2023 | HPHC Historical Preservation No Effect |
May 19, 2023 | Biologist Report |
May 24, 2023 | Modification Approved |
Jun 28, 2023 | Land Evidence Date |