Action Date | Action Description |
---|---|
HPHC Review Pending | |
Eng Team Review for Completeness | |
Bio Team Review for Completeness | |
Project Manager | |
Sep 08, 2022 | Assent Application Received |
Sep 08, 2022 | CHA Worksheet received |
Sep 13, 2022 | Bio Team Review for Completeness |
Sep 13, 2022 | Application Accepted |
Sep 13, 2022 | Project Manager |
Sep 13, 2022 | Administrative Review for Completeness |
Oct 07, 2022 | Plans Received |
Oct 07, 2022 | HPHC Historical Preservation No Effect |
Oct 19, 2022 | Biologist Report |
Oct 25, 2022 | Typist for Processing |
Oct 25, 2022 | Executive Sign Off |
Oct 25, 2022 | Sent to Photo Copy |
Oct 25, 2022 | Permit Approved |
Oct 25, 2022 | Permit Mailed |
Nov 17, 2022 | Land Evidence Date |
Nov 13, 2024 | Modification Request |
Nov 18, 2024 | Administrative Review for Completeness |