Action Date | Action Description |
---|---|
US Army Corps of Engineers Approval Received | |
Dec 06, 2022 | HPHC Historical Preservation No Effect |
Dec 06, 2022 | Dredge Application |
Dec 08, 2022 | Administrative Review for Completeness |
Jan 13, 2023 | Eng Team Review for Completeness |
Feb 13, 2023 | Application Accepted |
Feb 17, 2023 | Project Manager |
Mar 20, 2023 | HPHC Historical Preservation No Effect |
Oct 23, 2023 | 15 day Public Notice Issued |
Nov 07, 2023 | Public Notice End Date |
Nov 21, 2023 | Correspondence Received |
Nov 28, 2023 | Dredge Report |
Dec 04, 2023 | DEM Dredge Permit |
Dec 04, 2023 | Typist for Processing |
Dec 04, 2023 | Executive Sign Off |
Dec 04, 2023 | Sent to Photo Copy |
Dec 04, 2023 | Permit Approved |
Dec 05, 2023 | Permit Mailed |
Dec 15, 2023 | Land Evidence Date |
Nov 21, 2024 | Commencement of Work Notice received |