Action Date | Action Description |
---|---|
Land Evidence Date | |
Jan 31, 2024 | Assent Application Received |
Feb 07, 2024 | Administrative Review for Completeness |
Feb 23, 2024 | Bio Team Review for Completeness |
Feb 23, 2024 | Deficient Application - Owner Notification Sent |
Mar 15, 2024 | Correspondence Mailed/Faxed/E-mailed |
Apr 03, 2024 | Deficient Application Picked Up |
Apr 05, 2024 | Meeting Held |
Apr 12, 2024 | Note to File |
May 23, 2024 | Meeting Held |
Jun 14, 2024 | Assent Application Received |
Jun 18, 2024 | Administrative Review for Completeness |
Jun 21, 2024 | Bio Team Review for Completeness |
Jun 21, 2024 | Application Accepted |
Jun 21, 2024 | Project Manager |
Jun 27, 2024 | HPHC Historical Preservation No Effect |
Jul 08, 2024 | Additional Information Received |
Aug 15, 2024 | Correspondence Mailed/Faxed/E-mailed |
Aug 15, 2024 | Plans Received |
Aug 20, 2024 | Additional Information Received |
Aug 29, 2024 | Additional Information Requested from Applicant |
Oct 01, 2024 | Correspondence Mailed/Faxed/E-mailed |
Oct 04, 2024 | Additional Information Received |
Oct 18, 2024 | Biologist Report |
Nov 15, 2024 | Typist for Processing |
Nov 15, 2024 | Executive Sign Off |
Nov 15, 2024 | Sent to Photo Copy |
Nov 15, 2024 | Permit Approved |
Nov 19, 2024 | Permit Mailed |