Action Date | Action Description |
---|---|
Aug 18, 2004 | Application Accepted |
Aug 24, 2004 | Engineering Report |
Aug 31, 2004 | Permit Approved |
Aug 31, 2004 | Land Evidence Date |
Feb 01, 2021 | Modification Request |
Feb 12, 2021 | Administrative Review for Completeness |
Feb 25, 2021 | Bio Team Review for Completeness |
Feb 26, 2021 | Project Manager |
Mar 03, 2021 | HPHC Review Pending |
Mar 03, 2021 | HPHC Historical Preservation No Effect |
May 07, 2021 | 30 day Public Notice Issued |
Jun 07, 2021 | Public Notice End Date |
Jun 17, 2021 | Dock Meeting -- Approval |
Jul 16, 2021 | Plans Received |
Aug 05, 2021 | Stipulation Package from Biologist |
Aug 05, 2021 | Biologist Report |
Aug 06, 2021 | Typist for Processing |
Aug 06, 2021 | Executive Sign Off |
Aug 06, 2021 | Sent to Photo Copy |
Aug 06, 2021 | Modification Approved |
Jan 13, 2022 | Land Evidence Date |